Keith Foster's Master Plan includes slight alterations on ten greens to increase hole locations and playability. The plan for #2 and #4 greens is a bit more in-depth. The greens are being expanded and recontoured, the process is outlined below.
Photo of #4 Green before work began. |
![]() |
Keith Foster Master Plan drawings of green expansion areas for holes #2 and #4. The areas in green are expansions, the lines in red indicate new contours. |
The temporary backfill is removed and then drainage is installed. The base layer under the drainage pipe is filled with a layer of gravel. Tracking wire is laid alongside the pipe. |
Green liner is added to a depth of about 15 inches. |
A four-inch layer of gravel is installed over the drainage pipe. |
![]() |
Once the green is complete, bunkers will be shaped. |